In transformers there are two windings primary and secondary, but in some case you may see in addition to them one more winding named as tertiary winding.
This winding details were discribed in BS: 171-1959 as a delta winding used at a Star - Star Connected transformer or Auto transformer for any of the following usages;
Used to reduce the interference with communication circuit due to third harmanic currents in the lines and earth.
Used for facilitate the flow of Zero Phase Sequence Current
To reduce the third harmonic voltages in system and transformer
Injecting the reactive power for maintain the certain voltage level.( Tertiary connected with static capacitors or with synchronous condenser)
Auxiliary supply requirement at system which lower than primary and secondary winding voltages.
Its rating may be less apprx. 33.33% of main winding. This delta connected winding may be loaded or unloaded as per requirement. If it unloaded it called as stabilising winding. The design of tertiary based on the fault conditions.
1. It decides suitability of transformer to the system 2. It limits Short Circuit Current (Inversely) 3. It causes voltage drop (Directly)
For transformers up to 2 MVA it is around 5%, Above 2 MVA it varies up to 25% also.
Note: %Z is depends on Resistance value (%Z = V R^2 + X^2). Resistance value may affect with temperature, so, all resistance and Impedance values must convert in to standard temperature of 75%.
Engineers who are all working in Project as electrical cable, line works, installations etc.. must know the clearances between phase - ph and also ph- earth to maintain the minimum values.
All over the world VDE (Germany) standards are famous to follow, In India we are following the CBIP standards, For our reference the standard values as follows
VDE -VERBAND DER ELEKTROTEKNIK ELECTRONIK INFORMATIONS TECHNIK CBIP -Central Board of Irrigation & Power
I hope this may helpful to you all Engineers. We welcomes all your suggestions, ideas, views about posts/blog and feedback for any poor performance in this regard.
Whenever i am visiting site most of the ambitious persons asked me about What is percentage Impedance in Transformer? How to calculate Percentage Impedance in Transformer? Use of Percentage Impedance in Transformer? What is the relationship between % Z and Short Circuit current?
For all the above questions we will put end by today at this blog, but due to some other work i am unable, it is sure you will get those all at within a day or two.
Objective: Electrical Connections are very important if they improper it may cost the following effects on man and materials, and ready to destroy the whole system also, The poor connection in Bushing metal part causes the following,
Melting in any side of connections, usually low melting point material side.
Over heating in contact places
Over heating increases chances of early oil leak in bushings
Servicing difficult once the part melted/ burred
The over heating will affect the next weakest point which is near.
Once it start melt it is unable to replace it may possible to cut and remove the entire metal part then only it possible to change
Further detailed photos you may visit www.sagar33@vox.com
Magnetic Balance test used to find the distribution of Flux (Magnetic), Core Assembly Condition and defect in winding (If any).
It may check at HV Side or LV Side as per requirement/ site condition.
For Star Connection, apply the supply at U & N measure the values at V & N as well as W & N, then repeat the apply at V & N measure other two values, repeat it to apply at W & N.
For Delta connections, apply voltage must be in Phase - Phase like U & V, V & W and W & U.
For Ex:
U & N = (V & N) + (W & N); 240 = 198 + 42
Example : Results of 16 MVA, 110/ 33 KV Transformer, Vector Group of Dyn 11 (Delta Star 11)
Everyone knows before commissioning or charging any equipment it must be need to test before putin to service, like that the new transformer is also need to ensure everything is fine. So, some tests are required to confirm. those are all called Pre-commissioning tests.some important tests are mentioned here for easy ref,
i) Insulation Resistance or Meggar Value with PI (Polarization Index) ii) Turns / voltage Ratio iii) Magnetic Balance iv) Magnetizing current v) Oil tests (BDV, PPM and DGA (for future ref)) vi) Protections (Differential, IDMT, Bucholz Relay,OTI, WTI, PRV, OSR, MOG, Fans and pumps) vii) Operation of OLTC or OCTC/OCKT viii) Vector Group Test
As per IS 2026 the following Routine tests are carrying out in transformers at testing stage. 1. Measurement of Winding resistance 2. Voltage Ratio/ Ratio Test 3. Measurement of Impedance voltage/ Short Circuit impedance 4. Measurement of NO-Load loss and current 5. Dielectric tests (Induced Over Voltage and Separate Source Voltage) 6. Magnetic Balance and Current 7. Load Loss 8. Insulation Resistance 9. Vector Group 10. Oil BDV 11. Capacitance and Tan delta